Today I painted the pieces of woodwork for bay 2 in standard grey, these should be dry enough to assemble tomorrow. After that I finished the inner parts of the last three window frames and started making the sheet metal for the out part of the window frames.
Monthly Archives: January 2020
1/1/2020
Completed cutting the material for the inner flange of the window frames (the bit the glass abuts) and started to make up the remaining frames. I hope to complete the rest of the frames by the end of next week, however I am fitting this job around nearside paneling and frame repair so it may take longer.