Tag Archives: corner panels

14/05/2023

The interior of the destination box has been painted white and the matt black areas have been painted also.

The front dash panel (exterior) has been primed and sanded ready for undercoat.

The cab paintwork is largely finished now, only a few odd bits to do including a second coat for the main (front) floor panel and the O/S cove panel which has a hole and small dent to be attended to.  The first and second from rear O/S bays have lower panels fitted now, also the curved waist corner panel and the first bay waist panel are all on too.  The stainless corner bumper/embellisher has been fitted and the beading that finishes the rear panel has also been fitted.

1/1/2022 – Year summary for 2021

The last two weeks have seen the completion of repairs to the O/S frame, the last of the rusty screws and nails removed and the holes dowelled.   The last of the new flitch plated have been fitted.   The repairs to the cantrail have been sanded level and the rest of the frame sanded and prepared for painting.  The unpainted woodwork has been primed and the a start made on painting the whole of the exposed frame with grey top coat.

As it is the first day of the year, a summary of work completed in the last twelve months is appropriate.

The nearside of the bus from the entrance rearwards has been structurally completed, all windows panels are in place and beaded.  The rear corner panel has been cosmetically filled and finished in undercoat.  A new mudwing and liner was fabricated and installed and the wheelbox cover stripped, painted and refitted with new mountings.

The roof has been completely stripped of all paint and repaired where necessary to make it watertight.

The roof over the entrance and nearside front wheel has been repaired and is ready for cosmetic finishing, including a new valance over the entrance steps.

A new rear number plate box was fabricated and installed, along with new bulb holders and wiring for the stop and tail lights. The boot doors have been refitted and primed.

The destination box glass has been removed and a replacement obtained.  Some repairs have been made to the wooden frame that supports the glass.

The entrance step light was repaired and repainted ready for fitting.

The boot was finished internally with new lino.

Work has now commenced on the offside with all windows removed, frame repairs completed above the floor and the frame partially painted.

 

 

 

18/9/2021

Work on the nearside rear corner has been completed now and the panel has been primed and painted in undercoat, flatted and ready for top coat when the time comes.

The stainless steel corner bumper has been refitted along with the beading to the left of the boot doors.

After that, work turned to the offside with the removal of the rear most window adjacent to the emergency door.  The steel frame of this was heavily corroded so I have been welding replacement sections to create a new mounting flange.

NS rear corner, finished ready for topcoat

OS rearmost window frame as found, being prepared for repair