31/12/2024 and year summary for 2024

As this is Christmas and new year week, not much got done but I started the week by completing and testing the wiring of the boot light and its switch.  After Christmas, the first job was to update the plan for 2025.  When I got out to the bus shed, I primed the remaining cab woodwork as a prelude to painting, ready for fitting of the cab window.  I then cleaned and polished the fixed pane of the cab window and cut the remaining piece of steel channel for this pane.  I’m awaiting the arrival of some steel angle to complete this with the draught excluder.  I also primed the aluminium panel below the cab window on the inside of the cab door and some of the woodword on the emrgency door got a second coat.

As this is the last entry of the year, a summary of work completed in the last twelve months is appropriate.

All the offside half-drop windows were assembled and installed.

New window frames were  constructed and new glass fitted for the final  non-opening offside window and the emergency door window.  The cab offside window was glazed.

The emergency door was rebuilt with new exterior panels and the new window, then rehung and externally primed.

Attention was given to cab details, including the grab handles, fire extinguisher and holder, and the interior lights switch box which was repaired and painted.  Paint was stripped from under the front canopy.  A new panel was fitted to the inside of the cab door and the cab window frame  and slam lock repaired.

The seats were removed, and retrimmed in the correct moquette (sourced from Facebook appeals) and brown vinyl by Ifor Evans.  The driver’s seat was also retrimmed by Ifor.

On the electrical side, the indicator switch in the cab was partially cabled, the destination box had the bulb holders installed and wiring through to the cab completed.  The boot lamp was installed and wired up to a the switch and successfully tested.

The wheels had their tyres removed and the rims sandblasted and partially primed.

9/6/2024

Not  much visible progress this week, due to having a bad cold.  I have ordered the steel for the remaining window frames and arranged to collect the moquette from my brother.  Heard from Ifor Evans that the driver’s seat will be ready next week.  I cut out the former for the larger window from 1 inch block and finished it on the sander then cut out some holes for clamping the material.  Shot myself in the foot by not thinking about the smaller window and will no doubt end up having to cut a new former for that.  I then turned my attention to wiring and fitting the indicator switch in the cab, during which I was able to amend the wiring diagram I had prepared earlier.  In preparation for fastening the wiring to the frame in the cab, I repainted the cab grab handles to tidy them up as it will be difficult to do so after the wiring is installed.  Last small jobs were electrical, running the three-core cable for the indicators up from the terminal strip behind the front wheel into the cab.

21/4/2024

Started the week by painting the visible bit of the outer panel at the top of the cab side window opening and preparing the triangular window glass for installing  in the cab.  As I had some topcoat left over I painted the emergency door step and the top and leading upright of the cab door frame.  Next I started work on refurbishing the interior light switch box, removing the labels and cleaning them by knocking the awkward, tiny steel rivets.  A job to do in between others!  Next I fitted the fire extinguisher holder in the cab and polished up a fire extinguisher and placed it in the holder.  At the end of the week I started stripping the remaining original paint from under the front canopy, a difficult, slow job but i made good progress.  The last job of the work was completion of removing the labels from the switch box cover, ready for paint now.

Fire extinguisher fitted in cab and side window glazed.